This public preview demonstrates one narrow CivilQuant principle: geometry becomes a quantity through visible deterministic arithmetic, then stays linked to source and issue state. No account is required.

Sample workflow

Drawing entity → measured quantity → BOQ value → evidence

Change the wall dimensions and sample rates. CivilQuant recomputes the measurement and illustrative BOQ values in your browser.

A-201 · Rev C · Wall W04

Illustrative Gauteng demo assumption · user-editable
Illustrative Gauteng demo assumption · user-editable
Illustrative Gauteng demo assumption · user-editable
Estimating allowance only · not a bending-schedule takeoff

Transparency: the sample rates are illustrative 2026 Gauteng demonstration assumptions, not live market prices, a quotation, a formal estimate or a professional cost opinion. Formwork represents the two principal wall faces. Actual reinforcement must be measured from structural design information and/or the bending schedule.

W04
12.00 m
3.00 m
Concrete9.00 m³
Formwork (2 faces)72.00 m²
Reinforcement allowance1,080 kg
Sample totalR 99,090
BOQ itemUnitQtyRateAmount
In-situ concrete to wallm³9.00R 2,450R 22,050
Formwork to two principal wall facesm²72.00R 650R 46,800
Reinforcement — illustrative allowancekg1,080R 28R 30,240
Evidence chainReviewer required
  1. SourceA-201 · Rev C · Wall W04
  2. Measured geometry12.00 × 3.00 × 0.25 m
  3. Concrete formula12.00 × 3.00 × 0.25 = 9.00 m³
  4. Reinforcement allowance120 kg/m³
  5. Rate provenanceUser-entered illustrative Gauteng assumptions
  6. Issue stateDraft · professional review required
Important

This is a browser demonstration, not a formal takeoff, BOQ, estimate, valuation or professional opinion. CivilQuant's production value comes from connecting calculations to actual drawings, documents, rates, permissions and review workflows.